Arizona City Flood Hazard Mitigation Project

6/19/2014

Drainage improvements will take place on Battaglia Road and Henness Road.  The project will last several months.  From June 23, 2014 through January 23, 2015.  The work will consist of improvements to the existing channels along Battaglia Road.  There will be construction for a new low water crossing on Henness Road.  A box culvert will be put in and a detention basin on the southwest corner of Battaglia Road and Henness Road.  Road will be closed on Henness Road from Battaglia Road and Alsdorf Road.  Please use Lamb Road as an alternate.